Din l-Art Ħelwa would like to ask you to submit a formally signed quotation (Financial Bid) taking into consideration the details provided in the attached BOQ. The quotation should feature clearly the quoted fees, with excluding VAT, Vat and including VAT amounts. Bidders are committed to retain the validity of quotation for a period of ninety(90) days from the closing date for the submission of the RFQ.

Submissions are to include all the requested details and documentation and should be submitted via email by 29th February 2024

Late submissions will be rejected and will not be evaluated.

Interested bidders are to submit queries and questions concerning this RFQ to admin@dinlarthelwa.org

The relevant documents can be downloaded here. Full Development Permit for Delimara Lighthouse issued by the Planning  Authority, Delimara Lighthouse Restoration Method Statement, BOQ and Financial Bid.

Work will have to be conducted between 1st October and 30th November 2024